Project and Contract Forecasts

Overview

Alasco distinguishes between project and contract forecasts. Both types can be presented in the real case and the worst case. Both the project and contract forecasts are based on costs.

 

Project forecast

The project forecast is used to make quick statements about the success of the project as a whole. The project forecast is displayed in the following places in Alasco:

  • For the whole project in the financial overview on the dashboard
  • For an individual trade on the detail page of a contract unit 
  • In the cost controlling for individual contract units, cost groups or the whole project.

You will find the project forecast in the cost monitoring as the two columns, "Project Cost Forecast (Real Case)" and "Project Cost Forecast (Worst Case)".

You can display the deviation from the current budget in absolute values and percentages against the real and worst case scenarios of the project forecast with the columns "Project Budget Deviation Real/Worst Case" and "Project Budget Deviation Real/Worst Case (%)".

 

Calculation of the project forecast

The project forecast is calculated by summing up all the data for a contract unit and depends primarily on the status of the contract unit.

Since either the current budget or the contract forecast is used, project forecasts can only be calculated at the contract unit level (or higher) and not at the level below (contracts).

The status of the individual contract units defines whether the "current budget" or "contract forecast" will be used for the forecast.

Contract unit with the status Budgeted

As long as a contract unit has the status "Budgeted", the project forecast corresponds to the current budget of the contract unit.

The status "Budgeted" indicates a relatively early point in the course of the project or during the planning process, at which time usually no contracts have yet been awarded.

For this reason, the system assumes that you will also completely use up the previously calculated budget, which is why this is used as the project forecast.

Contract unit with the status Fully Awarded or Finalized

As soon as a contract unit has the status "Fully Awarded" or "Finalized", the project forecast is based on the more precise contract forecast of the contract unit.

The contract forecast is calculated based on the contracts within the contract unit and can be individually adjusted in the forecast settings within the master data.

The status "Fully Awarded" indicates some or all of the contracts within the contract unit have already been awarded; some contracts may even be already completed.

The contract unit automatically assumes the status "Finalized" as soon as all contracts receive a "Completed" status. This can be done manually or through the approval and payment of the final invoice.

After the status has been changed, the individual contract forecast is used to calculate the project forecast, and a distinction is made between the real-case and worst-case forecasts.

Contingency contract unit

Contract units of the type "Contingency" are an exception in the calculation of the project forecast. Their current budgets are always included in the worst-case project forecast.

Note:

If your Alasco account was created before calendar week 42 (2020), the old calculation logic will be available. In the master data, admins can select under the menu item "Project forecast settings" whether the old calculation logic "predefined" or the new "configurable (recommended)" calculation method should be applied. This setting applies to the entire Alasco account.

A detailed list of the differences can be found in the following article in our Help Centre: Predefined Project Forecasting (no longer recommended).


Contract forecast

The contract forecast is used to make quick statements about a single contract. The contract forecast is used to calculate the project forecast once the contract unit is "Fully Awarded" or "Finalized", as described above.

You will find the contract forecast in the cost controlling as the columns "Contract Cost Forecast (Real Case)" and "Contract Cost Forecast (Worst Case)".

You can also display the deviation from the current budget in absolute values and percentages against the real and worst case scenarios of the contract forecast with the columns "Contract Budget Deviation Real/Worst Case" and "Contract Budget Deviation Real/Worst Case (%)".

 

Calculation of the contract forecast

The contract forecast is calculated by adding or subtracting all relevant values of a contract. Which values are added or subtracted as part of the contract forecast can be freely configured for the real and worst case scenarios by an admin in the master data under the menu item "Forecast settings". These settings apply to the entire Alasco account.

Depending on the status of a contract, either the maximum of target vs actual costs or only the actual costs are used to calculate the contract forecast.

Contract with the status Draft, Ordered or Partially Completed

As long as a contract has the status "Draft", "Ordered", or "Partially Completed", it depends on whether the sum of the target costs or the actual costs is higher.

The target costs come from the contract volume; the actual costs correspond to the paid invoices. Detailed lists for both target and actual costs can be found below.

Contract forecast (real case) = maximum of target costs or actual costs (real case)

Contract forecast (worst case) = maximum of target costs or actual costs (worst case)

Contract with the status Completed

As soon as a contract has the status "Completed", the contract forecast corresponds to the actual costs, i.e. the approved invoices.

Contract forecast (real case) = actual costs (real case)

Contract forecast (worst case) = actual costs (worst case) 

Target costs

Target costs include the following data from a contract unit or contract:

  • Draft contracts
  • Main contracts
  • Acknowledged change orders
  • Open change orders
  • Reserves
  • Risks
  • Planned receivables
  • Realized receivables

In the master data, under the menu item "Forecast settings", an admin can define the individual items that should be added to the contract forecast for the real and worst case scenarios. Receivables can be subtracted.

Contract_forecast_target_costs.png

Note:

Please note that in Alasco all target and actual costs included in the real case forecast must also be included in the worst case forecast.

Conversely, all costs deducted in the worst case forecast must also be deducted in the real case forecast. The respective checkbox is greyed-out and can only be changed once the other checkmark has been removed from the respective forecast.

Actual costs

Actual costs include the following data of a contract:

  • Approved invoices
  • Contractual retentions (general and defects liability retentions)
  • Other retentions
  • Planned receivables
  • Realized receivables

In the master data, under the menu item "Forecast settings", an admin can define the individual items that should be added to the contract forecast for the real and worst case scenarios. Receivables can be subtracted.

Note:

Please note that in Alasco all target and actual costs included in the real case forecast must also be included in the worst case forecast.

Conversely, all costs deducted in the worst case forecast must also be deducted in the real case forecast. The respective checkbox is greyed-out and can only be changed once the other checkmark has been removed from the respective forecast.

 

New: Consideration of contract terms and cash discount

In addition to the calculation logic of the forecasts mentioned above, you have the option to decide whether contract terms, such as deductions, cost allocations, insurances or cash discounts, are considered in the contract forecast.

If you activate this option in the forecast settings of the master data, the deductions for each contract are deducted from the target costs. No distinction is made between the real and worst case forecasts. The contract terms are calculated identically in both scenarios.

The actual costs are not affected, as the contract terms were already considered during invoice verification.

In principle, the contract terms, provided they are taken into account in the target costs, are subtracted as follows:

(Target contracts + main contracts + acknowledged change orders + open change orders) - contract terms

The subtraction of deductions, cost allocations and insurances is calculated the same way during the invoice verification. For the cash discount, you can define whether you want to subtract only the already realised cash discount or the total potential cash discount in the contract forecast.

Subtract realised cash discount

If you select the option "Subtract realised cash discount", which is set as default, the cash discount actually taken from all paid invoices of a contract will be subtracted from the contract forecast. The cash discount amount corresponds to the amount entered during the workflow.

Note:

In the last workflow step, "Pay invoice", you have the option to pay the "Approved amount less cash discount" or you can enter a different payment amount in the field "Other amount". This could be the case, for example, due to rounding differences.

If this deviating payment amount is within a tolerance of +- 5 cents of the released amount minus cash discount, the cash discount is considered as a "realized cash discount". Otherwise, the invoice is evaluated as if no cash discount was applied.

Subtract potential cash discount

If you have selected the option "Subtract potential cash discount", the maximum possible cash discount amount from all contracts is subtracted from the contract forecast. Therefore, you can see the minimum amount you will have to pay if you approve and pay each invoice within the cash discount period.

As soon as an invoice is not paid within the cash discount period, the contract forecast is corrected by the corresponding unrealised cash discount.

Note:

Please note that these settings only apply to standard and multipart contracts. For recurring invoicing contracts, the forecast is calculated without considering contract terms and cash discounts.

LEGAL

Was this article helpful?
1 out of 2 found this helpful

Comments

0 comments

Please sign in to leave a comment.

Articles in this section

We are here for you
We are happy to support you personally from Monday to Friday between 9.00 am and 5.00 pm.